Road workBy EVE LEBERSON
© St. Petersburg Times, 1. INTERSTATE 275, from Busch Boulevard to U.S. 41, will have periodic night-time lane closures. Also watch for construction at Busch Boulevard and Fowler Avenue near the interstate. Work will continue until two new lanes are complete in Fall 2002. 2. BINDER ROAD, from Gunn Highway to its end, will have lane closed for roadway widening until Sept. 30. 3. LINEBAUGH AVENUE, from Plantation Boulevard to N Dale Mabry Highway, will have intermittent lanes closed for roadway improvements until July 31. 4. 22ND STREET, from 132nd Avenue to 131st Avenue, will be closed for intersection improvements until July 31. 5. FLETCHER AVENUE, under Interstate 275, might have nightly lane closures until July 29. 6. BEARSS AVENUE, under Interstate 275, might have nightly lane closures until July 29. 7. NORTH BOULEVARD, just south of Fletcher Avenue, will be closed for stormdrain improvements until Friday. © 2006 • All Rights Reserved • Tampa Bay Times
490 First Avenue South St. Petersburg, FL 33701 727-893-8111
|
From the Times |
![]()